When base material becomes a bottleneck: What PCB customers can do now

Content you may also like

Bild zeigt ein Frachtschiff an einem abendlichen Containerterminal

A PCB's lead time does not begin only when production starts. It also depends on whether glass fabric, resin, copper foil, and the required base material are available on time. If any of these materials becomes scarce, available production capacity alone cannot guarantee the planned delivery date.

Supply is constrained by high demand and limited capacity. Demand is especially high for high-performance materials, and additional production capacity cannot be brought online quickly. PCB customers therefore need to make their requirements visible early, prepare technical alternatives, and factor material availability into their planning.

Rising demand meets limited material capacity

The expansion of AI data centers is increasing demand for high-performance PCBs and the materials they require. Compared with conventional applications, AI systems require several times as much base material. Materials in demand include specialized resins, glass fabric, and copper foil.

Other applications rely on the same material and manufacturing capacity. These include high-frequency and high-reliability applications, satellite communications, and future mobile network infrastructure. Competition is therefore not limited to available production time; it also affects the availability of qualified materials.

Material lead times extend planning horizons

According to market data compiled in November 2026, material lead times for standard FR-4 are currently around 10 to 12 weeks. For specialty materials, they can reach 24 to 30 weeks. These lead times apply to the base material and come before PCB fabrication and shipping.

Availability is particularly tight for certain prepregs. Type 1080 glass fabric is sold out in many places. At some manufacturers, incoming material supplies cover only part of planned monthly output. This can lead to backlogs and temporary production stoppages.

When reviewing delivery schedules and capacity, it is therefore worth looking beyond the PCB manufacturer or production site. It is also essential to confirm that the required, qualified material will be available on time. Production options in Southeast Asia do not automatically solve the problem if material is unavailable.

Pricing and allocation are changing purchasing decisions

The cost of base materials has risen sharply. According to market data compiled in November 2026, cumulative price increases for base materials are around 400% by the fourth quarter of 2026 compared with mid-2025. By mid-2027, the cumulative increase is estimated to exceed 600%. Further increases have been announced.

These figures do not apply across the board to every material or PCB. Prices depend on factors such as material type, construction, availability, and the specific quotation. In a tight market, companies should consider material allocation, supply capability, quality, and potential effects on their own production, as well as the unit price.

Base material manufacturers are prioritizing high-performance AI and high-frequency materials. Some low-end and standard materials are being withdrawn from the market or are available only with little advance notice. Materials with a Tg of 135 are currently affected, and Tg 150 materials are also coming under increasing pressure. Alternatives approved in advance, along with a coordinated technical assessment, provide more flexibility.

New capacity will not ease pressure in the short term

Base material manufacturers are expanding capacity, but this is not expected to ease the situation quickly. Building and commissioning new glass furnaces can take up to three years. Investment, construction, and ramp-up therefore will not automatically close a short-term supply gap.

Current demand signals suggest that the expansion of AI infrastructure will keep demand for advanced materials high in the coming years. Satellite communications, non-terrestrial networks, and future mobile network infrastructure could increase demand further. A rapid return to normal conditions should not be treated as a reliable planning assumption.

What PCB customers can do now

The market situation cannot be resolved through planning alone in the short term. Early coordination can give companies more room to act:

  • Extend the forecast horizon. Share rolling demand forecasts and release quantities as early as possible. The sooner demand is visible, the easier it is to coordinate material procurement and production planning.
  • Assess technical alternatives in advance. Work with your engineering team and PCB partner to determine which base materials are essential and which alternatives are technically viable. Approving alternatives early can provide more flexibility if the originally specified material becomes scarce.
  • Review the stackup and prepregs early. Check prepreg dependencies, especially for 1080, 2116, and 7628, as well as impedance requirements. Avoid unnecessary overspecification and late design changes.
  • Assess supply and price together. When materials are allocated, choosing based only on the lowest price can increase the risk of delayed material availability. Consider availability, quality, total cost, and potential effects on your own production together.
  • Consider inventory arrangements for recurring demand. For predictable series requirements, a coordinated stocking or blanket order arrangement can improve supply security and reduce your own inventory. Quantities, materials, and call-off terms depend on the specific requirements and individual agreement.

How Würth Elektronik CBT Asia Production can help

Würth Elektronik CBT combines a network of strategic partners and production facilities in Asia with teams in Germany and Asia. Its offering ranges from qualified prototypes to larger production runs. Testing and quality processes, along with a Quality Design Center, support supply chain assessment and assurance.

Würth Elektronik CBT also operates a PCB logistics center at its German headquarters. Agreed PCB orders and blanket orders can be stored there and called off as needed. This can reduce the need for customers to hold their own inventory and make already-produced PCBs available closer to where they are needed. The suitability of this approach depends on the specific requirements and individual agreement.

Plan early and prepare alternatives

Material shortages cannot be resolved simply by changing the production location at short notice. Companies that make their needs visible early, assess technical alternatives in advance, and consider supply and price together can better manage the risks to their own planning.

Would you like to review material dependencies or a potential alternative for a specific PCB project? Contact your usual sales representative at Würth Elektronik CBT.

Note: The market figures, forecasts, and availability statements above come from the submitted draft and have not been independently verified. They may vary by manufacturer, material, specification, and project. Before publication, confirm their currency, source approvals, and the verification points mentioned above internally.